E3D-APAM-RPT-002 · Board Condition Report · Board 30 of 67
DB-JGSESW
GSE apron board
RED — Major defect
Status: Complete · Condition Index 26.3/100

1. Verdict & suitability

Assessment summary

Can house the new LED luminaires & controlsYES — universal
BasisLED load ≪ legacy HID; enclosure space & isolation adequate
Overall condition ratingRED — Major defect
P2
2
P3
2
P4
0
Photos
12
0Condition Index 26.3100

Rated RED. The board can house the new LED works. Field condition records significant structural / enclosure damage and non-compliant working-space clearance.

2. Location

N Apron boards · this board highlighted
GPS (lat, long)-37.677939, 144.848409
Zone / apronTo be confirmed against apron key-plan
Upstream source (parent DB / sub)To be confirmed against airfield reticulation drawings
Inspected21–22 June 2026

3. Supply & electrical

As-built supply and cabling recorded on site. Visual / physical condition audit only — no electrical testing performed.

Incoming supply & earthing
Supplied fromDB Gate 28
Upstream CB way(s)—
Phases3-phase
Line voltage400 V (L-L)
Phase-earth voltage230 V (L-N)
Earthing systemReticulated
Upstream protectionIsolator only (no OCPD confirmed at board)
Supply cable schedule
Active conductor size16 mm²
Configuration1x4C
Conductor arrangementcircular
Parallel sets1
Conductor materialCopper
Insulation / typeXLPE
ArmourUnarmoured
Installation methodUnderground Enclosure
Conduit100 mm
Loaded circuits in conduit—
Estimated depth0.5 m
Earth arrangementSeparate — 16 mm²
Approx. lengthNot recorded
Field note (open supply query): See defect — resolve looped-vs-dedicated feed arrangement on the F-series 50 mm mains before finalising the outgoing design.

4. Condition assessment

Scored per the Condition Scoring & Rating Model (six standards-referenced dimensions, 0–4 on the P-scale). Rating is gated — a single safety/structural P2 breach sets RED regardless of the averaged Index.

DimensionScoreGradeObservation
Electrical safety & compliance0None observedNone observed
Structural & enclosure integrity3Major / safety (P2)Enclosure & chassis mechanical integrity
Corrosion & protective coating0None observedNone observed
Ingress protection0None observedNone observed
Access & working space3Major / safety (P2)Door opening arc and working-space clearance
Thermal / fire & component0None observedNone observed
Rationale. The gated rating is RED, driven by structural / enclosure damage and a non-compliant door / working-space clearance (AS/NZS 3000 Cl 2.10) (Condition Index 26.3/100). RED reflects a gate breach — a safety/structural P2 or an AS/NZS 3000 Cl 2.10 clearance non-compliance — that cannot be averaged away.

5. Defects

Field-observed defect(s) for this board, itemised into discrete findings — each with its own priority and category.

RefCategoryDefectPri
D-01 Structural Structural damage to enclosure P2
D-02 Structural Interim support brackets in place (temporary repair) P3
D-03 Clearance Non-compliant door / working-space clearance P2
D-04 Clearance Additional bollards recommended at rear of plinth (delineation / physical protection) P3

6. Suitability for the LED works

Suitability for LED worksYES

The new LED floodlight load and driver footprint are materially smaller than the legacy HID gear removed, and the existing 3-phase supply, 16 mm² feed and cabinet isolation are adequate for the new works. This conclusion is universal across the fleet and is independent of condition.

7. Photographic evidence

12 site photographs. Frames outlined in orange are keyed to a priority defect (fire, structural, access or ingress evidence).

Site photo
Site photo #1
Site photo
Site photo #2
Site photo
Site photo #3
Site photo
Site photo #4
Site photo
Site photo #5
Site photo
Site photo #6
Site photo
Site photo #7
Site photo
Site photo #8
Site photo
Site photo #9
Site photo
Site photo #10
Site photo
Site photo #11
Site photo
Site photo #12